Fabrication and installation of metal structures for a 130-ton bucket elevator tower, Vinnytsia region, 2018.
In 2018, VITANT GROUP successfully implemented a project to manufacture and install steel structures for a bucket elevator tower with a total weight of 130 tons in Vinnytsia region. This facility is an important element of the agro-industrial infrastructure, as it ensures efficient transportation and cleaning of grain crops.
Stages of work performance
-
Design and calculation of structures
- Engineering calculations of loads
- Development of CMM drawings taking into account the specifics of the object
-
Fabrication of metal structures
- Incoming inspection of rolled metal products
- Cutting, drilling and welding of parts
- Quality control of welded joints
-
Corrosion protection
- Cleaning metal from scale and corrosion
- Painting and applying a protective coating
-
Installation work at the facility
- Delivery of metal structures
- Installation of the elevator tower using special equipment
- Bolted and welded connections, precision control
-
Final testing and commissioning
- Checking the stability and reliability of structures
- Load testing
- Transfer of the finished object to the customer
Result
Thanks to the professional approach of VITANT GROUP, the project was completed on time and in accordance with all building codes and standards. The elevator and cleaning tower ensures stable and safe operation, which increases the company’s productivity and contributes to the efficient processing of grain crops.